Worker A takes 8 hours to do a job. Worker B takes 10 hours to do a job. How long should it take both A and B, working together to do same job?
A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it
A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?
A does a work in 10 days and B does the same work in 15 days. In how many days they together will do the same work ?
A can finish a work in 18 days and B can do same work in half the time taken by A. then working together, what part of same work they can finish in a day
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B alone can do the whole work in
A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how long does it take both the punctures together to make it flat?
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
If m men can do a work in p days, then the number of days taken by (s +n) men to do it is
A machine P can print one lakh magazine in 8 hours, machine Q can print the same number of magazine in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh magazine) be finished ?
Men can do a certain work in 15 days. They started working on the project but 5 of them leave after every five days. In how many days will the work be completed now?
P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?
5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio
If daily wages of a man is double to that of a woman, how many men should work for 25 days to earn Rs.14400? Given that wages for 40 women for 30 days are Rs.21600.
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?
Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?